Upozornění: Text přílohy byl získán strojově a nemusí přesně odpovídat originálu. Zejména u strojově nečitelných smluv, kde jsme použili OCR. originál smlouvy stáhnete odsud
Contract for Work
concluded
according to
§ 2586
and subs
.
law
no. 89/2012 Coll
.,
the
Civil Code
,
as
amended
I.
Contractual parties
1.
University of Chemistry and
Technology
,
Prague
having
its office at: Prague
6,
Technická
5,
Zip Code
166 28
, Czech Republic
acting
by:
xxxxxxxxxxxxxxxx
,
Bursar
bank
connection
:
Č
eskoslovenská
obchodní
banka
,
a.s
.,
(
“ČSOB
a.s
.”
) A
cc
ount
N
o
.:
for
E
UR payments:
xxxxxxxxxxxxxxxxxxxxx
for
USD payments:
xxxxxxxxxxxxxxxxxx
for
other payments:
xxxxxxxxxxxxxxxxxxxxxxxxx
SWIFT/BIC CODE: CEKOCZPP
IdNo
.
:
60461373
Tax Registration No.
: CZ60461373
hereinafter
C
ontractor
1.
MOTIM Fused Cast Refractories Ltd.
Head Office:
Timföldgyári
u. 9-13, H-9200
Mosonmagyaróvár
, Hungary
Recorded in the Commercial Register at
Győr
-
Moson
-Sopron County, Hungary under
No. 08-09-009091.
Name and surname of statutory body or its members, or else of another person authorised
to
act on behalf of the legal entity: G
eneral Manager:
xxxxxxxxxxxxxxxx
Bank connection:
IBAN:
HU
xxxxxxxxxxxxxxxxxxxx
BIC/Swift: UBRTHUHB
Raiffeisen Bank
Rt
.,
Akadémia
u. 6., H-1054 Budapest,
Hungary
ID No.: 12524516
Tax ID No: HU12524516
Hereinafter only the Customer
II.
Subject matter of the contract
1.
The subject matter of the contract is
C
orrosion behavio
u
r of the materials ZIRKOSIT-
S32,
ZIRKOSIT-M36 and ZIRKOSIT-
Y41
i
n the contact with a glass
melt
hereinafter
the Work.
The Work includes sample preparation and performing of the following laboratory tests:
Static
corrosion
plate test with
ZIRKOSIT-
S32,
ZIRKOSIT-M36 and ZIRKOSIT-
Y41
at 1
45
0°C
(6 samples),
Refractory exudation test with
ZIRKOSIT-
S32,
ZIRKOSIT-M36 and ZIRKOSIT-
Y41
at
1650°C
(6 samples),
Static blistering test with
ZIRKOSIT-
S32,
ZIRKOSIT-M36 and ZIRKOSIT-
Y41
at 1
45
0°C
(6 samples).
1.
The
C
ustomer
declares that the work of this contract is directly related to his subject of enterprise listed in his trade authorization and he
undertakes
to use the
W
ork only for purposes directly related to this subject of enterprise.
III.
Time schedule and place
1.
The
Contractor
is obliged to complete the W
ork
till
March 31, 2017
1.
The W
ork shall be performed on the site:
University
of
Chemistry
and Technology, Prague
,
Technická
5, 166 28 Prague, Czech Republic
IV.
Obligations and rights of the
C
ustomer
1.
The Customer will provide the Contractor for the execution of the Work necessary documentations and materials to the Laboratory of Inorganic Materials,
University
of
Chemistry
and Technology, Prague
,
Technická
5, 166 28 Prague, Czech Republic
.
2.
The
Customer
undertakes
to take delivery of the
Work
immediately after the
Contractor
delivers him
a
written
notice about
Work
execution.
V.
Obligations and rights of the
Contractor
1.
The
Contractor
is obliged
to perform the
Work
in person
,
at
his own
expense
and
at his own risk in the agreed period of time.
1.
When performing the
Work
the
Contractor
acts independently and is not bound by
Customer
’s instructions.
1.
The
Contractor
is not allowed to
delegate the
Work
to another person.
If another person
performs the
Work
, the
Contractor
has the same responsib
ility
as if he performs it himself.
1.
The
Contractor
as a
storer
is liable for
a
subject matter received from the
Customer
for lodge in order to perform its processing when perfor
ming the
Work
or in order to repair or modify it
(§2415
and
foll
.
law no.
89/2012 Coll
.,
of the Civil Code
).
The
Customer
bears the risk of damage to this subject matter as long as his ownership title to this subject matter lasts.
VI.
Price of Work and Payment conditions
1.
The agreed price for the
Work
shall be
:
a)
price
without
VAT
11 600,- EUR
Detailed:
Refractory corrosion plate
tests at 1450°C: EUR 1800,-
Thin sectioning and optical microscopy: EUR 1800,-
Refractory exudation tests at 1650°C: EUR 2 000,-
Static blistering test at 1450°C: EUR 5 700,-
Samples preparation: EUR 300,-
2.
The
Customer
is obliged to pay to the
Contractor
the price for the
Work
,
the
Contractor
has
the
right for price payment since
a
moment of the
Work
completion. The price for
Work
, listed in art.
VI/1.
of
this contract
,
is an exercise price and it may be increased if the
Contractor
proves unavoidably increased and together appropriately expended expenses which
had
ar
isen
during
execution of this
Work
or in context of it without its infliction.
Increase of the price
shall be agreed by the
Customer
in form of a written amendment to this contract.
3.
The price includes all activities and supplies of the
Contractor
necessary for first-class performance of the
Work
according to this contract.
4.
Value added tax is invoiced by the
Contractor
to the
Customer
in
an
invoice which creates a basis for payment of the price for the
Work
and this tax.
5.
The price for the
Work
and value added
tax are
due within
30
calendar days after the invoice had been delivered to the
Customer
. The invoice is issued by the
Contractor
immediately after the
Work
is delivered and received
.
The invoice shall contain terms of
a
tax certificate acco
rding to law no. 235/2004 Coll
., on value added tax, in the current version. The price is paid when the paid amount is placed to the
Contractor
’s account, listed in art.
I. of this contract.
For EU foreign taxpayers the reverse-charge model will be used.
6.
If the
Customer
shall be in default with
payment of the price for
the
Work
, the
Customer
shall pay
a
penalty equal to
0.1
%
from the due amount for each such day of default.
The parties preclude the usage of § 2050 of the Civil code.
VII.
Additional provisions
1.
Persons responsible for performing duties according to this contract are these employees of the
1.
Contractor
:
xxxxxxxxxxxxxxxxxxxxx
1.
Customer
:
xxxxxxxxxxxxxxxxxxx
1.
The
Contractor
retains the right to provide the data about eventual research report coming out of this contract for
Work
to the Register of information on the results
according to the Act no. 130/2002 Coll., on support of research and development from public funds and
changes of other related laws as amended.
1.
If the result or
a
part of the
Work
performed according to this contract is a result which is being protected by
an
industrial property law or another intellectual property law
, the
Customer
is entitled to use it only for purpose implied hereof. For further use the
Customer
is obliged to conclude with the
Contractor
a relevant licensing contract.
1.
Responsibility for defects shall be governed by § 2615 and
foll
.
of
the Civil Code.
1.
Each contractual party is entitled to withdraw from the contract in case that the opposite contractual party commits a breach of the duty to which this contract bounds it, or even terminate it for convenience. The contractual party which has committed a breach of the contractual duty is obliged to make good the damage to the opposite party including appropriately expended costs incurred to the opposite party in the consequence of the withdrawal of this contract. If this contract is terminated for convenience, the duty belongs to the terminating party. The termination of the contract is effective since a written notice about termination of the contract is delivered to the opposite contractual party.
1.
All notices between contracting parties
related to this contract or notices which shall be done under this contract have to be done in written form and delivered to the opposite contracting party personally or by mail to the address listed in art. I. of this contract, unless it is agree otherwise by the contracting parties.
1.
The contracting parties
consider any notice related to this contract as properly delivered:
a)
In case of
personal delivery or by courier:
aa
) the date of real
take-over of the notice by the recipient; or
ab
) the date when the notice is delivered to person designated to take over the correspondence on the recipient´s address; or
ac
) the date when the notice is delivered to person designated to take over the correspondence on the recipient´s address and this person refuses to take over the correspondence.
b)
In case of delivering by mail:
ba
) the date
of real take-over of correspondence by the recipient; or
bb
) the date of the first attempt of delivery of correspondence when the recipient doesn´t take over the correspondence for any reason or refuses to take over the correspondence when there is delivery address written on the correspondence.
VIII.
Final provisions
1.
This contract may be modified and amended on
ly in form of written numbered a
mendments to this contract, signed by both contractual parties.
2.
This contract shall enter into force and shall take effect on the day when it is signed by both contractual parties.
3.
If any provisions of this contract are or will become invalid, unenforceable or ineffective, this invalidity, unenforceability or ineffectiveness does not affect other provisions of this contract. The contracting parties undertake to replace
invalid, unenforceable or ineffective provisions by valid, enforceable and effective provisions
with the same commercial or legal sense or to sign a new contract
within five (5) working days from
delivery of the notice to opposite contractual party.
4.
The contracting parties expressly confirm that the terms of this contract are the result of negotiations of
contracting parties and both contracting parties had the opportunity to influence the content of the basic conditions of this contract. This contract includes the entire arrangement about the subject matter of this contract and all the formalities that the contracting parties should or wanted to negotiate in the contract and which are
considered to be important for binding effect of this contract. No act of contracting parties made during the negotiation about this contract or after signing this contact
shall not be interpreted in contradiction with explicit provisions of this contract and does not establish any obligation of any contracting party. The con
tracting parties do not wish that any rights or obligations would go beyond explicit provisions
adjusted
by this contract or would be influenced by existing or future experience
between
contracting parties or
by traditions usual for sector concerning the subject matter of this contract, unless it is expressly agreed in this contract. Furthermore the contracting parties confirm that they are not aware of any established traditions
or commercialism. The answer of contracting party, under § 1740
par.
3 law no. 89/2012 Coll., of the Civil Code, as amended,
is not considered as
acceptance of
the offer for conclusion or modification of this contract, even if it does not substantially change offer conditions. For the avoidance of doubts it is mentioned that contracting parties consider this contract as courageous and therefore
the provisions of the Civil Code of changed circumstances (§ 1764 to 1766) and disproportionate shortening (§ 1793 to 1795) do not affect
the obligat
ions arising from this contract.
The contracting parties exclude the application of the provisions of § 557 and 1805 par. 2 law no. 89/2012 Coll., of the Civil Code, on the contractual relationship adjusted by this contract.
5.
Legal relationship not expressly adjusted in this contract shall be governed by the legislation in force of the Czech Republic, especially by the provisions of the Civil Code.
Any
disputes
between contracting parties arising from this contract shall be first resolved amicably if possible. If an amicable solution is not reached, the disputes will be resolved by the competent court.
Dispositive provisions of generally binding legal regulations in force in the Czech Republic, which are in conflict with the provisions of this contract, shall not be used.
6.
The contracting parties
acknowledge that this contract is subject to the legislation of the law no. 340/2015 Coll., on the registry of contracts, and therefore this contract will be disclosed in the registry according to § 4 of this law.
7.
The contracting parties hereby declare that they agree with the content of this contract, understand this contract and are committed to its
fulfilment. The contracting parties sign this contract and declare that this contract was concluded according to their free and serious will.
8.
This contract had been made in 2 duplicates
as originals
whereby each contracting party shall retain one copy each.
In Prague on
…………………………………
….
……………………………
On behalf of the
Contractor
On behalf of the
Customer