                        Contract No: 0100-SM-N0028-21

CONTRACT FOR TESTING OF MEASURING INSTRUMENTS

                                                             I.
                                                  Contractual parties
The contract is hereby concluded between:

SUBMITTER:

Name of corporation or natural person: El Sewedy Electrometer Egypt Co. S.A.E

Principal office of corporation:        Plot no. 154/173 – 2nd Industrial Zone, 6th of October

                                        City, 12451, Egypt

Company registration number:            367405806

Tax identification number (VAT):        367405806

Represented by:                         quality manager Ibrahim Abdel Aziz

Authorized person to technical negotiations: Ibrahim Abdel Aziz

Hereinafter referred to as „Submitter“

                                        and

PROVIDER:                         Czech Metrology Institute (Cesky metrologicky institut)
Principal office:                 Okruzni 31, Brno, PC: 638 00
Legal form:                       state contribution organisation established by the foundation deed of the
                                  MH CR file No.521 385/92-44 dated 21.12.1992 according to the adjusted
Company registration number:      foundation deed issued on the basis of the resolution of the Ministry of
Tax identification number:        Industry and Trade No. 16/2009 file No. 21943/02/4001/1000 dated
Bank connection:                  10.3.2009
Affiliated branch:                00177016
Number of the account:            CZ00177016
IBAN:
SWIFT:                            Dr. Pavel Klenovsky, Deputy Director for Fundamental Metrology
Represented by:
Hereinafter referred to as „CMI”

The contracting parties declare that data stated in this article of the contract comply with relevant
entries in the Commercial register or the Trade registry, respectively in any other evidence as required
by law and that the persons stated here above are the authorised representatives.

The contracting parties appointed persons authorised to act in matters referring the subject of this contract:
a) on behalf of the Submitter :
b) on behalf of the Provider:

                                 Express statement of the contractual parties

The Parties hereby declare and acknowledge that the above-stated information is accurate and correct.
The Parties are obliged to notify the other contracting Party of any changes within ten working days.
The contractual Parties are making a contract in accordance with § 1746/2 of the Civil Code of the
Czech Republic as amended.

                                                                                                                1/5
                                                      II.
                                       Subject-matter of contract
1. The subject of this contract is the performance of the below mentioned metrological tests on
    two samples of three phase electricity meter XXXXX:
      a) Limits of error due to variation of the Current,
      b) Test of no-load condition,
      c) Test of starting condition,
      d) Test of power consumption,
      e) Influence of Self-Heating test,
      f) Influence of Ambient Temperature Variation,
      g) Resistance to heat and fire test
    These tests will be performed according to the standards IEC 62052-11, IEC 62053-22 and
    IEC 62053-23.
2. The Submitter has to organize the transport of measuring instruments to business premises of
    CMI and from business premises of CMI back at one's own expenses and at one’s own risk.
    CMI has to arrange the transportation between CMI’s laboratories at the expenses of the CMI
    and at one’s own risk. The expenses of the transportation between CMI’s laboratories are
    concluded in the contractual price.
3. The Submitter will provide the cooperation and the information for the purposes of the
    objective testing. The subject – matter of the contract will be considered fulfilled by the
    issuing the test report. The Submitter undertakes to receive the subject matter of the contract
    and to pay for it the contractual price.

                                                      III.
                                    Place and time of performance
1. The place of the performance is negotiated in the business premises of CMI. The Submitter is
    undertaken to transfer the measuring instrument to CMI at the negotiated place and
    coincidently to transfer against confirmation.
2. CMI shall carry out the testing of measuring instruments by 31st August, 2021. The period of
    the default of the Submitter (for example: do not delivering needed documents, software) will
    extend the time of the performance. The term of delivering measuring instruments has to be
    agreed in advance. The obligations of CMI are fulfilled by the testing of measuring
    instruments and issuing the test report.

3. In case when the instrument fails in any phase of the testing procedure, the testing shall
    be suspended and the corresponding costs shall be invoiced to the Submitter. In this
    case no protocol shall be issued. The testing will be resumed after the invoice is paid and
    modified samples delivered. The time of execution as given in the contract starts to run
    anew as of the delivery of the modified samples. The testing will be resumed after the
    invoice is paid and modified samples delivered. The time of execution as given in the
    contract starts to run anew as of the delivery of the modified samples.

                                                                                                         2/5
                                                      IV.
                             Contractual price and methods of payment

1. The contractual price for the performance is 3.365,- EUR (without VAT) and it was
    determined in accordance with provisions of The Act on prices No 526/1990 Coll., as
    amended.

2. The contractual price will be determined according to provision of the Value-Added Tax Act
    No. 235/2004 Coll. as amended. The Submitter is obliged and he undertakes to pay the
    charged price for metrological services in agreed term by credit transfer on the basis of issued
    current tax voucher, containing data set in Act No. 235/2004 Coll., as amended. The
    Submitter agrees to pay all bank pay all bank charges related to the payment for the purpose
    of the contract, so the amount specified in article no. IV.1. above is credited in favour of
    Provider’s account in the whole (not reduced by any fees). If applicable, the SEPA rules shall
    prevail (only transfers within the EU).

3. The contractual price conclude only expenses direct connected with the testing. The
    contractual price do not include expenses connected with the transportation, customs and
    other costs. The expenses for the transportation (in the case that the Provider will arrange it)
    will be invoiced to the Submitter in the actual incurred amount (It will be proved by the
    copies of the documents.).

4. The invoice maturity date lies on the 30th day after its expedition to the Submitter. The date
    of payment is considered to be the date on which the invoiced sum of money is credited to the
    CMI's account.

                                                      V.
                                      Charges for overdue services

1. In case of the delayed payment of the invoice the penalty from the contractual price in the
    amount of 0,03 % for each day of delay is determined.

2. In case of the delayed metrological performance the penalty from the value of the non-
    performance metrological achievement in the amount of 0,03 % for each day of delay is
    determined.

3. This stipulation does not affect possible right of the contracting parties to compensation of
    suffered damage as established due to non-fulfilment of liabilities from the contract.

                                                      VI.
                                  Vis major and liability to damages

1. The parties are exempted from their liabilities for the entire or partial non-performance of
    their obligations (with the exception of delayed payments according to the contract
    conditions) in case it is the result of vis major circumstances.

2. The Party that is referring to the vis major circumstances shall notify the other Party in
    writing in a 5 /five/-day-period from the date of their occurrence.

3. Upon the formal announcing of termination of vis major circumstances, the Parties shall
    discuss their contractual obligations and shall make mutually beneficial decision on the
    further performance of the Contract.

                                                     VII.
                                  Force of contract and termination

1. This document sets forth the entire agreement and understanding between the parties as to the
    subject matter of this Agreement, and merges all prior discussions between them. The
    contract becomes valid upon the signature of the parties.

                                                                                                         3/5
2. The contractual parties are making a contract for a determined period. The effect of the
    contract is terminated by the fulfilment of obligations arising out of this contract.

3. The CMI is also entitled to terminate the contractual relation established by this contract in
    the form of a written agreement or by written notice without stating the reasons, while the run
    of the 20 days notice period starts as from the first day of the week following the delivery to
    the other contracting party. Termination of this contract does not affect the liability of
    contracting parties to settle all and any existing liabilities established on the basis of this
    contract, all of that in the course of one month as from the contract termination, at the latest.

4. This contract can be changed with written amendments signed by duly authorized
    representatives of both parties. Notwithstanding the foregoing, upon the breach of any
    condition of the agreement by any party, or in the event that any party becomes bankrupt or
    insolvent, or makes a transfer in fraud of creditors, or makes an assignment for the benefit of
    creditors, or takes or has taken against it any proceedings of any kind under any provision of
    any insolvency, bankruptcy or reorganization act, the other party shall have the right to
    terminate this agreement immediately by so notifying the first party. Their obligations to the
    day of withdrawal must be fulfilled. All Notices or other communications under or in
    connection with this Agreement shall be made in writing and unless provided otherwise, may
    be made by letter or by fax. Any notice shall be considered made, provided that:

   a), if it is a letter, it is delivered by hand or by recommended post,

   b), if it is a fax, it is received in a legible form.

   Notices sent in accordance with the foregoing but received on a public holiday or after
   business hours shall be considered delivered on the next business day.

                                                     VIII.
                                           Other arrangement

1. The participants of this contract conclude an agreement according to § 1746/2 Civil Code
    stating, that their above-stated liability relations as per this contract follow the Civil Code of
    Czech Republic.

2. The CMI is obliged to take appropriate care for entrusted measuring standards and to protect
    them against stealing, abuse or damaging, all of that even towards third persons.

3. The CMI is not responsible towards the Submitter for damages caused on entrusted
    measuring instruments that were caused by the tests.

4. The CMI is responsible towards the Submitter for damages caused on entrusted measuring
    instruments that were caused by improper handling, by negligence or intentionally. In such
    cases, the CMI is obliged to provide the Submitter with compensation of caused damages by
    putting the device into its original conditions or by compensation of costs spent on its repair,
    all of that maximally to the sum of the insurance money paid by the insurance house.

5. The CMI undertakes not to pass any part of the service to any other metrological institute
    (sub-contractor), unless it is stipulated in the contract or in an amendment to the contract.

6. In relation to this contract, the contracting parties undertake to arrange protection of business
    secret in compliance with Civil Code. Such information will not be communicated to any
    third person without written consent of the other contracting party. The given party will
    arrange in an efficient way for such information not to be abused. The obligation of
    confidentiality is valid for the time of this contract fulfilment as well as after its termination
    with consequences set by the legal regulations for the case of jeopardizing or breaching the
    rights and obligations.

                                                      IX.
                                              Final provisions

                                                                                                         4/5
1. Both of the contracting parties are obliged actively and without unnecessary delay inform
    each other about occurrence of facts that could affect efficiency of the contract or its
    individual stipulations or quality and terms for fulfilment of obligations emerging from the
    contract.

2. The contracting parties will solve possible disputes related to the contract fulfilment mainly
    by mutual negotiations of representatives or statutory authorities, usually in 14 calendar days
    as from the date of a written notice or reminder of one of the contracting parties. In case of
    such dispute not to be solved by agreement, the disputable matter will be solved through court
    of Czech Republic.

3. In compliance with stipulation of §89a Civil Court regulations, the participants concluded an
    agreement, respectively they agreed on other venue of the first level court. The venue court is
    the court of the first level in the district of headquarters of the Czech Metrology Institute.

4. All duties and obligations of the Parties as well as any legal relations arising of this Contract
    shall be governed by Laws and Regulations of the Czech Republic.

5. If any provisions at this contract is declared void by any court of competent jurisdiction such
    provision shall be deemed severed from this contract and said contract shall otherwise remain
    in full force and effect.

6. Having read the contents the participants of the contract declare that they agree with its
    contents, they conclude the contract on the basic of their free, serious and definite will which
    they conform by their own hand signatures.

7. This agreement was written in 2 copies, each of which having the validity of an original. Each
    participant of the agreement will receive one copy.

Annex No 1 – Power of attorney - in the case that the contract will be signed by the another
person that is not authorised to sign the contract according to excerpt from the Business Register
of Submitter

On behalf of the Provider:              On behalf of the Submitter:

Date:                                   Date:

Stamp:                                  Stamp:

--------------------------------------  --------------------------------------

                                                                                5/5