Textová podoba smlouvy Smlouva č. 4177016: Smlouva o dílo - Personal Safety Interlock System

Příloha P3b-Schedule of Deliverables.docx

Upozornění: Text přílohy byl získán strojově a nemusí přesně odpovídat originálu. Zejména u strojově nečitelných smluv, kde jsme použili OCR. originál smlouvy stáhnete odsud



                        Schedule of Deliverables

	No. 
	Description
	Output
	Time of completion

	D0
	Kick off meeting
	Functional safety management plan
	4 weeks from Full Documentation handover

	D1 
	Risk analysis
	Risk analysis + SIL classification
	6 weeks from Full Documentation handover

	D2
	Safety requirements specification (SRS)
	SRS
	6 weeks from Full Documentation handover

	D3
	Design of the PSI system
	PSI design
	12 weeks from Full Documentation handover

	D4
	HW and SW factory tests
	Factory accepted HW and SW
	20 weeks from Full Documentation handover

	D5
	HW delivery to Client facility
	Delivered HW
	22 weeks from Full Documentation handover

	D6
	PSI system installation (plus integration intoto previously implemented Phases if applicable)
	Installed and site accepted PSI system
	28 weeks from Full Documentation handover

	D7
	Validation of allready installed system Phases
	Validated PSI system
	31 weeks from Full Documentation handover

	D8 
	Finalized documentation handover
	User documentation  (including maintenance plan, user manual, maintenance manual), As built technical documentation (including documented source code, calculation/verification of SIL), Documentation of the project management (including Project management plan, verification-validation plan, verification-validation documentation, etc.)
	34 max weeks from Full Documentation handover

	
	Tools and software for further development, maintenance and diagnostics handover
	Tools and software for further development, maintenance and diagnostics including needed licences, source codes or documentation